Orlando Avenue Improvements Update #1B – 7.11.18

The Contractor has begun to “core out” the existing roadway, which is the first step in the process of constructing the new pavement structure. The process involves removing what is left of the existing pavement structure (i.e., the existing pavement and stone), and placing the new stone base in preparation for the curb and gutter improvements.