Scott Lane, Juniper Lane and Cadet Road Improvements – Construction Update #3A – August 8, 2018

The total reconstruction of Scott Lane between Juniper and Heron, and Juniper Lane between Mildred and Cameo. Reconstruction will include new storm sewer, new curb/gutter and pavement structure, new driveway approaches and associated restoration. The project also includes new storm sewer improvements along Scott Lane, Juniper Lane and Cadet Roads to remedy the flooding that occurs in these locations. Finally, the project includes the removal and replacement of the existing pavement of Cadet Road between Harlem and Heron, Scott Lane between Harlem and Juniper, and Juniper Lane between Scott and Mildred, as well as miscellaneous sidewalk and curbing repairs.