April 21, 2014

  • Contractor will continue with the jack and bore of the casing pipe under Perryville Road north of IL 173.
  • Contractor will begin water main work between FHR and Perryville Road—that work will be later in the week.
  • Contractor will be working on Perryville Road beginning today to remove the median and place temp pavement.
  • There will be night closures for storm sewer laterals again this week.
  • Tree removal will continue this week (and by the way, if you have not driven east of Mitchell Road along IL 173 it is a worthwhile trip…..many of the trees are down and it really makes a difference)
  • Mass earth moving operations are tentatively scheduled to begin this week—later in the week.